Aylesbury Town Home Aim & Trackplan Base Boards Track Laying Buildings Scenics

Latest Goings On April 2018:

Photos by Steve Lovett

In recent weeks we’ve had the opportunity for full modelling days; Good Friday and last weekends Modelling Saturday. These have proved very fruitful with good tracklaying progress being made. At close of play on Saturday we have achieved the following:

This hasn’t always been without frustration as we have met challenges with baseboard joints, through line alignment and underestimation of those simple tasks which become little more challenging. We are still learning as we go but our confidence is growing. With our sights clearly on ‘FestiRail Model Railway Exhibition’ (7th July) we must be mindful of what we need to do to provide an operational layout:

Below laying and ballasting of the hand made track on the scenic section, this replaces the temporary laid double track for RISEX 2018, at the Modelling Saturday on the 14th April.

Latest Goings On February 2018:

Video & Photos by Anthony Mead

A short video clip, showing the first trains in action on the temporary laid double track for RISEX 2018, filmed at the Modelling Saturday on the 10th February.

A couple of photos of the whole layout setup, as it can be seen it only just fits length ways in the Carrington Room.

Progress to Date – 05 February 2018 by Steve Lovett

It's now some weeks since my last update at the AGM in November last year and considerable progress has been made on the Aylesbury Town layout.

You will recall that we saw RISEX 2018 as being the first opportunity to have the layout operational albeit with a temporary double loop. I am pleased to say that given the superb efforts of the project team we are almost there!
We have had our challenges though including:

Thankfully whilst irritating these are now sorted (famous last words) and did not detract from our successes where we have seen considerable progress on:
In fact it was a really pleasant change to finish last Friday (2 February) with a chat and a brew, as opposed to our more usual struggling with a short/gauging/woodworking issue.

This coming Modelling Saturday (10 February) will give us a full day to rehearse how we’re going to build/operate/teardown at RISEX on 17 February; we envisage 5 phases: build, test, trial, operate, teardown.

There is also great anticipation of the hope to have the inaugural formal full loop run at around 11:00, so cameras / videos at the ready. There won't be a dry eye in the clubroom so hankies at the ready.

Of course there some pre-RISEX challenges including working out a sequence for displaying available rolling stock (station stops/one train at the front/trains passing at the front etc) as well the inevitable repairs/modifications to carry out on the day but we are now used to such challenges.

Looking beyond RISEX our efforts will be concentrated on firstly 'mothballing' the non-scenic boards before starting on the scenic section of the layout where there is considerable tracklaying to be done (with all the associated electrical stuff), platforms to be built, buildings to be finalised and positioned, platforms built, scenery laid and the considerable amount of rolling stock to be built. Enough to keep us going for a wee while......

As ever the opportunity is there for you to get involved and share with us your knowledge and expertise so don't hesitate; this is after all a club layout.

Latest Goings On January 2018:

Photo by Anthony Mead

Work being undertaken on the Quainton end curved section, which links the scenic section to the fiddle yard during one of our Club nights in January. The race is on to have two complete circuits working for our Risex 2018 exhibition on the 17th February.

Steve, David, Paul, Chris, Mark, Mick and Tim checking the track work.

Latest Goings On November 2017:

Photo by Anthony Mead

Track testing work being checked on the fiddle yard boards at one of our Club nights in November.

Kevin, Steve, Neil, Peter and Chris checking the track work.

Progress to Date – 10th November 2017 by Steve Lovett

In early June 2017 a ‘stock taking exercise’ of the Aylesbury Town project was undertaken which sought to figure out what the next steps were to be and what needed to be done following the loss of our friend and colleague Phil Baxendale.
It was apparent that we were starting with a layout that had:

It was considered sensible to complete tracklaying and the full electrical installation, testing and commissioning on the non-scenic fiddleyard boards before commencing on the scenic section. This decision was made recognising the space available within the clubroom, the need to complete and mothball sections of the layout and the numbers of members available at any working session. The task has taken longer than we initially envisaged although is now concluding.
That said in August 2017 the layout saw its first test locomotive running on two of the fiddle yard boards. Since then there has been considerable progress with operational testing and commissioning on many fiddleyard boards, making lineside buildings and early progress on signal construction.
This achievement is the culmination of many months of hard work and the recent progress made on the non-scenic baseboards includes:

However whilst such success is welcomed there is still much to do.

Short Horizon (December 2017 - February 2018)

Our immediate priority is to work towards our aspiration to have a part - operational layout at RISEX in February 2018 albeit only a double track circuit - for this to happen the layout will need to be fully supported with suitable trestles, trial running beforehand with sufficient DCC equipment available.

Medium Horizon (February 2018 to August 2019)

Baseboards

Non Scenic Boards The main scenic boards have not been forgotten though with points substantially complete and plain line construction eagerly anticipated (even if it does mean that we have to thread thousands of miniature chairs!).

Scenic Boards Longer Horizon (May 2020) Lessons learned

There’s no such thing as a simple straightforward task.
Never underestimate the frustration when trying to identify and resolve an electrical short – follow Mick’s wise words “TEST AS YOUGO!”

Open Saturday July 2017:

Photos by Anthony Mead

Work being undertaken on the fiddle yard boards at our Open Saturday on the 8th July.

Kevin and Tim wiring the fiddle yard.

Tim checking a suitcase connector.

Tim, Kevin and Steve checking for shorts.

Latest Goings On July 2016:

Photos by David Lane

On the 22nd July, all the completed baseboards where set up in the main room in the Community Centre. The photos were taken on David's phone, and with the light streaming through the windows have not come out too well, but give you some idea of scale, there are two ten coach trains on the layout and as can be seen these are lost. The trestles are just temporary, as the board storage boxes and legs will support the layout. David also keeps a thread on RMWeb,about the layout.